Sunday, 8 June 2014

The Pool

As the redevelopment continues the outdoor pool is now closed and filled in. This will make way for a landscaped courtyard (available on completion of redevelopment)



Sunday, 11 May 2014

The Demolition

Phase 1 - Demolition & rebuild of the Washington wing  - 03rd March 2014  -  09 June 2015
Demolition of Washinton Wing  - 01 September 2013 to 31 October 2013 - COMPLETED
Rebuild /expansion of Wahington Wing - 01 November 2013 to 15 October 2014 - In progress

  • Work will commence between the hours of 8am and 6pm, Monday to Friday
  •  Heavy machinery, including Bull Dozers and Cranes will be used from September to June
  •  False walls (Hoardings) has been erected to cushion noise levels and dust through out the hotel
  • Inventory has been reduced from 208 rooms to 159 rooms
  • Hotel pool facility will be indefinitely closed from 01 September 2013
  •  Contractors will have minimal access to hotel public areas.







 Washington wing about to be demolished.


Washington wing demolished



 
        Demolition of Washington Wing

       Demolition and clearing of site almost complete.

Tuesday, 27 August 2013

The Revedelopment

SUDIMA CHRISTCHURCH AIRPORT
25 MILLION RE-DEVELOPMENT PROJECT
WELL UNDERWAY!

Sudima Hotels New Zealand, is delighted to announce that the re-development of its iconic Christchurch Airport hotel is now well underway.

As with many projects of this magnitude and in particular in Christchurch, planning and resource consent for the demolition of the original accommodation wing and the refurbishment of other areas of the hotel, has taken longer than expected.

Sudesh Jhunjhnuwala, owner of Sudima Hotels commented recently “Sudima Hotels, is delighted to play its role in contributing to the growth and rebuilt phase of this wonderful city, the gateway to the South Island, by investing close to 25 million in the re-development of Sudima Christchurch Airport, which at completion, will provide first class quality accommodation and conference facilities, servicing all segments of the market both domestically & internationally”.

Whilst the re-development project in its entirety is not expected to be completed until early 2016, the first stage of the project, including the opening of the newly built accommodation wing housing 89 rooms, upgraded lobby and reception, refreshed conference facilities and redesigned façade of the hotel, is earmarked for completion by early to mid-2015. During that time, management wants to reassure all of its loyal customers that the property will continue to operate with as little disturbance as possible, however with a reduced inventory of 158 rooms.


At completion of the entire re-development project planned for 2016, the new look Sudima Christchurch Airport, will boast a total of  247 rooms, a new look exterior and public areas making it one of Christchurch’s finest hotels backed by unparalleled customer service which Sudima hotels are renowned for.