As the redevelopment continues the outdoor pool is now closed and filled in. This will make way for a landscaped courtyard (available on completion of redevelopment)
Sudima Christchurch Airport $25 million re-development 03 March 2014 to 2016. To stay up to date please subscribe by entering your email address below:
Sunday, 8 June 2014
Sunday, 11 May 2014
The Demolition
Phase 1 - Demolition & rebuild of the Washington wing - 03rd March 2014 - 09 June 2015
Demolition of Washinton Wing - 01 September 2013 to 31 October 2013 - COMPLETED
Rebuild /expansion of Wahington Wing - 01 November 2013 to 15 October 2014 - In progress
- Work will commence between the hours of 8am and 6pm, Monday to Friday
- Heavy machinery, including Bull Dozers and Cranes will be used from September to June
- False walls (Hoardings) has been erected to cushion noise levels and dust through out the hotel
- Inventory has been reduced from 208 rooms to 159 rooms
- Hotel pool facility will be indefinitely closed from 01 September 2013
- Contractors will have minimal access to hotel public areas.
Demolition of Washington Wing
Demolition and clearing of site almost complete.
Tuesday, 27 August 2013
The Revedelopment
SUDIMA
CHRISTCHURCH AIRPORT
25 MILLION RE-DEVELOPMENT PROJECT
WELL UNDERWAY!
25 MILLION RE-DEVELOPMENT PROJECT
WELL UNDERWAY!
Sudima Hotels
New Zealand, is delighted to announce that the re-development of its iconic Christchurch
Airport hotel is now well underway.
As with many
projects of this magnitude and in particular in Christchurch, planning and
resource consent for the demolition of the original accommodation wing and the
refurbishment of other areas of the hotel, has taken longer than expected.
Sudesh
Jhunjhnuwala, owner of Sudima Hotels commented recently “Sudima Hotels, is delighted
to play its role in contributing to the growth and rebuilt phase of this
wonderful city, the gateway to the South Island, by investing close to 25
million in the re-development of Sudima Christchurch Airport, which at
completion, will provide first class quality accommodation and conference
facilities, servicing all segments of the market both domestically & internationally”.
Whilst the
re-development project in its entirety is not expected to be completed until
early 2016, the first stage of the project, including the opening of the newly
built accommodation wing housing 89 rooms, upgraded lobby and reception,
refreshed conference facilities and redesigned façade of the hotel, is
earmarked for completion by early to mid-2015. During that time, management
wants to reassure all of its loyal customers that the property will continue to
operate with as little disturbance as possible, however with a reduced inventory
of 158 rooms.
At completion of
the entire re-development project planned for 2016, the new look Sudima
Christchurch Airport, will boast a total of
247 rooms, a new look exterior and public areas making it one of
Christchurch’s finest hotels backed by unparalleled customer service which
Sudima hotels are renowned for.