Phase 1 - Demolition & rebuild of the Washington wing - 03rd March 2014 - 09 June 2015
Demolition of Washinton Wing - 01 September 2013 to 31 October 2013 - COMPLETED
Rebuild /expansion of Wahington Wing - 01 November 2013 to 15 October 2014 - In progress
- Work will commence between the hours of 8am and 6pm, Monday to Friday
- Heavy machinery, including Bull Dozers and Cranes will be used from September to June
- False walls (Hoardings) has been erected to cushion noise levels and dust through out the hotel
- Inventory has been reduced from 208 rooms to 159 rooms
- Hotel pool facility will be indefinitely closed from 01 September 2013
- Contractors will have minimal access to hotel public areas.
Demolition of Washington Wing
Demolition and clearing of site almost complete.