Sunday 11 May 2014

The Demolition

Phase 1 - Demolition & rebuild of the Washington wing  - 03rd March 2014  -  09 June 2015
Demolition of Washinton Wing  - 01 September 2013 to 31 October 2013 - COMPLETED
Rebuild /expansion of Wahington Wing - 01 November 2013 to 15 October 2014 - In progress

  • Work will commence between the hours of 8am and 6pm, Monday to Friday
  •  Heavy machinery, including Bull Dozers and Cranes will be used from September to June
  •  False walls (Hoardings) has been erected to cushion noise levels and dust through out the hotel
  • Inventory has been reduced from 208 rooms to 159 rooms
  • Hotel pool facility will be indefinitely closed from 01 September 2013
  •  Contractors will have minimal access to hotel public areas.







 Washington wing about to be demolished.


Washington wing demolished



 
        Demolition of Washington Wing

       Demolition and clearing of site almost complete.